Manufacturing throughput time is the total duration required for a product to move through the entire manufacturing process, transforming from raw materials into finished goods. This concept also extends to the processing of raw materials into components or sub-assemblies.
#Effective Cycle Time
Average time it takes to produce one good part/batch
Using OEE (Overall Equipment Effectiveness) :
Effective Cycle Time=OEEDesigned Cycle Time
The above formula can be reduced to:
Effective Cycle Time=Uptime Percent×Yield PercentActual Cycle Time
#Processing (value-add) time
Total of the node effective cycle times
Processing Time=EffectiveCycleTime1+EffectiveCycleTime2+…+EffectiveCycleTimen
#Inventory (queue) time
Total time it takes to process the inventory held between nodes
InventoryTimedays=Daily Customer RequirementInventory Held
where
Daily Customer Requirement=Operating Days Per WeekUnits Per Week
InventoryTimedays=Units Per WeekInventory Held×Operating Days Per Week
This is an approximate inventory time based on the value stream target performance. The actual inventory time will be closer to the number of units in inventory times the longest effective cycle time of any node in the system.
Units per week is defined at the value stream level. Operating days per week can be defined for the downstream node of the edge/relationship. Otherwise it falls back to the operating days per week defined at the value stream level.
#Manufacturing Throughput Time
Average total time it takes to produce one good part from start to finish
MTT=Processing Time+Inventory Time
#Units
The standard unit used for these calculations is seconds. However as times increase seconds becomes less helpful and moving to larger units is needed.
Example: 34,567 seconds is difficult to comprehend. Converting this to 9.6 hours is more helpful.
#Larger units (future)
For longer manufacturing throughput times we may want to also display days or weeks, taking into account the shift duration for each node.
SecondsPerDayn=(ShiftLengthn−BreakTimen)×ShiftsPerDayn
MTTdays=SecondsPerDay1EffectiveCycleTime1(1+InventoryHeld1)+SecondsPerDay2EffectiveCycleTime2(1+InventoryHeld2)+…+SecondsPerDaynEffectiveCycleTimen(1+InventoryHeldn)
Then the weeks can be calculated by dividing by the number of operating days per week:
MTTweeks=Operating Days Per WeekMTTdays