The recipe says what goes into a part. The floor doesn’t always follow it: a spacer gets dropped, a bracket is out of stock, a housing needs two extra shims. Threaded keeps the recipe as the plan and records each difference on the unit, with a reason. The result is an as-built record of what actually went on: each part, the lot or serial it came from, and who fitted it when.
#What it is
Each part on a recipe is made or bought, and counted or serialized:
| Made | Bought | |
|---|---|---|
| Counted | A bracket, a cut harness | Bolts, sealant, tape |
| Serialized | A sensor built in the plant, with its own serial | A purchased module with its vendor’s serial |
A made part has a route in your plant, and its finished output waits as stock. A bought part comes from outside and has no stock in Threaded.
When a unit arrives at a station, the station reserves the recipe’s share of each part for the unit’s build parts. Nothing leaves stock until Complete, which draws what was reserved, less anything marked not used. Made parts are drawn from their lots, oldest first. Bought parts go on the as-built record with no lot.
#Rules
- Run is turned on per organization. See Feature Access and Billing.
- The recipe belongs to the plant. A run never changes it. Adds, swaps, scraps and parts not used are recorded on the unit, each with a reason.
- Only Complete and a scrap move stock. Everything else changes what’s reserved.
- A made part is short at a station when more of it is reserved there than is on hand. The station, the floor map and feeder work orders all use the same count. Bought parts are never short. A part from a store that pulls (kanban, supermarket) shows as a pull, not short.
- A serial is used once, anywhere in your organization: fitted to a unit or scrapped.
- Adds, swaps and scraps are available while the unit is at the station and not on hold.
- Each add and swap can be deleted before Complete. A scrap can’t be deleted or reversed.
- After Complete, the visit is closed. A wrong part on a finished unit is fixed with rework.
#In the app
#Parts & materials
Parts & materials on the station page lists what the station uses for this unit: each recipe part with its quantity, its tools, and whether enough is on hand. Collapse folds the list down to the lines you fill in, and Show {items} shows the rest again.
#Pick serials
Each serialized part on the recipe is one line with one field for all its serials. The field takes the recipe share for the whole batch: a probe that takes 1 sensor, in a batch of 5, takes 5 serials.
- A made part gets a checklist of the serials on hand, oldest first, with the columns Serial, Work order (the order that made it), Product reason and Built from. Tick several, or type a work order or reason to find its serials. Serials held for another unit aren’t listed.
- A bought part has no stock to list, so type or scan its serials into the same field.
- Every serial field has a camera button. Scan a serial reads a barcode or QR code into it.
Each pick is saved as you make it, so it’s still there after a reload, on another device or the next day. A picked serial is held for its unit until Complete draws it, it’s marked not used, it’s scrapped, you take it off, or the unit leaves the station.
The station can’t complete until every serial spot has a pick.
#Serials from outside the plant
Sometimes a piece on the bench didn’t come from your stock: one the customer sent, one salvaged from a return, or one built before you ran on Threaded. Type or scan its serial anyway. When nothing in the list matches, the field offers {serial} isn’t in stock. Add it from outside the plant. Choose it, and the pick shows an Outside the plant chip.
- Your plant’s own serials (
u-1234) come only from stock. One that isn’t on hand is refused. - Nothing is drawn for a serial from outside the plant, and it’s never short.
- At Complete, it’s listed under Deviations. Accept it with a reason, and it goes on the as-built record as Outside the plant. If you don’t accept it, the unit is held.
- Bought parts’ serials are always typed, so they’re never from outside the plant.
#Add a part
Use More › Add a part when a unit needs a part its recipe doesn’t give: extra shims to fit a housing, a second bead of sealant, a bracket the drawing left off.
- Choose the part. Parts at this station are listed first, then Other parts from the work order’s plant. You can’t add the part the unit makes.
- Enter the quantity, or pick the serials, and a reason.
An add is reserved for the unit and drawn at Complete with the recipe share. Each add is its own record, and an add never adds build parts. A part counted each is added in whole numbers; a part measured by length, weight or volume can be added in part. A large quantity is limited to catch typos: to add more, add again.
You don’t need an add to replace a scrapped part. A scrap doesn’t change what the station has reserved, so Complete already draws the full recipe share.
#Swap a part
Use More › Swap a part to use one part in place of one recipe part on this unit: the station is out of it, one is damaged, or an engineer wants another tried on this build.
- Choose the recipe line to swap, the part to use instead, and a reason.
- Each swap replaces one piece for one piece. To use the new part for 4 of a line’s 10 bolts, swap 4 times. A part measured by length, weight or volume is swapped whole.
- On a serialized line, choose which picked serial comes off. Then pick a serial of the new part in its own field.
Both parts must be counted, or both serialized, in the same unit of measure. You can’t swap in a part already on the station’s recipe (that’s an add), and you can’t swap a part you added or swapped in. When one part is replaced by several, swap for the main replacement and add the rest.
The as-built record shows each swapped-in part with what it replaced and why.
#Scrap a part
Use More › Scrap a part for a part spoiled before it goes on: a dropped spacer, a torn gasket.
- A made part comes out of stock at once, oldest lot first or from the serial’s lot. If you scrap more than the lots have, the rest is logged with no lot.
- A bought part is logged.
- Several serials can be scrapped at once from the same checklist. A scrapped pick comes off its line, and its spot needs another pick before Complete.
- The station’s reservations don’t change. Take a replacement off the shelf; Complete draws it.
A scrap of a part isn’t a scrap of the unit. The batch keeps every build part. To scrap build parts, see Scrapped build parts; to scrap a held unit whole, see Working a Station.
#Delete an add, swap or note
Adds, swaps and notes from this visit are listed under Notes, scrap and material changes, with who made each. Each has an × to delete it until Complete. A confirm says what changes, for example “2 Shim come off what’s reserved.” No reason is asked.
- Deleting an add takes it off what’s reserved. An added serial is released.
- Deleting a swap gives the piece back to the recipe part. Adds made with the swap stay.
- A scrap has no ×.
#Not used
At a station that collects scrap, the Complete dialog’s Quantity and parts tab has a Material consumption table:
| Column | Meaning |
|---|---|
| Planned | The recipe share for the unit’s build parts |
| Added | What was added at this visit |
| Not used | What didn’t go on |
| Consumed | Planned + Added − Not used |
Mark a part Not used when a scrapped part wasn’t replaced, or when an added part turned out not to be needed. For a serialized part, tick the serials that didn’t go on; they’re released for any unit. Bought counted parts always go on whole.
At a station that doesn’t collect scrap, there’s no Not used: Complete draws everything reserved.
#Scrapped build parts
At a station that collects scrap, the Complete dialog asks how many build parts were Scrapped, and why. Each scrap group can name the serials those build parts carried. Naming them is optional; the record then shows which serials were scrapped and which went on.
#Rework and parts
On a second pass through a station, the recipe parts already drawn there aren’t drawn again: they’re still fitted. Only parts never drawn at that station, such as after a hold, take picks and are drawn. A part replaced during rework is an add at that pass, and the part it replaces is a scrap.
#The as-built record
After Complete, the unit’s record shows what went on at each station: each part, its lot or serial, the work order that made it, and every add, swap, scrap and deviation with its reason. See Work Orders, Units and Records.
#From the CLI or API
Use threaded api call with these operations. See What Run Exposes.
run_format_station_materials_retrieve: a station’s parts for a unit: reserved, on hand and short.run_format_units_reserve_serials: pick serials.run_format_addable_parts_listandrun_format_units_add_part: add a part.run_format_units_swap_part: swap a part.run_format_units_scrap_part: scrap a part at a station.run_format_units_delete_part_changeandrun_format_units_delete_note: delete an add, swap or note.